Fix 50 Update: Crews Focus On Outside Lanes Of Eastbound U.S. Highway 50May 5, 2014 | Marianne RussThe first eastbound phase of the Fix 50 project in Sacramento is finished. That included resurfacing and repairing the three inside eastbound lanes.
Fix 50 Recap: Crews Working On Phase 2 Of ProjectMay 2, 2014UPDATED: The Fix 50 project in Sacramento is ahead of schedule. Drivers had to adjust to different lane closures today as the project moved to a second stage. Listen /Update RequiredTo play audio, update browser or Flash plugin.
New Fix 50 Closures For Friday Morning CommuteMay 1, 2014 | Marianne RussIf your commute includes highway 50 in the Sacramento area, there are some new eastbound closures you'll want to be aware of starting tomorrow morning.
First Phase Of Fix 50 Project Ahead Of ScheduleApril 30, 2014 | Marianne RussCalTrans says the Fix 50 project in Sacramento is five days ahead of schedule.
Fix 50: Caltrans Lowers Speed Limit At Fix 50 Construction ZoneApril 28, 2014 | Bob MoffittCrews continue work on the Fix 50 project in Sacramento Monday morning. Contractors are working 24 hours a day to repair and resurface the W/X section of highway 50 in the heart of the city.
Fix 50 Construction Zone Accident Injures 3 WorkersApril 23, 2014 | Bob MoffittUPDATED: Three construction workers were injured Wednesday morning when a semi-truck hit a piece of lumber sticking out in traffic.
Fix 50: Some Slowdown Reported But Traffic Is FlowingApril 23, 2014Sacramento's "Fix 50" construction project has entered day two, and traffic is slow in the area where CalTrans is repairing and resurfacing the elevated section of highway 50. Some eastbound lanes are closed.
Fix 50 Day-One Morning RecapApril 22, 2014 | Bob MoffittAs expected, lane closures on the eastbound side of U.S. 50 through Sacramento caused delays for people commuting. People who sat through the delays and some people who found alternate routes considered doing something differently the next time. Listen /Update RequiredTo play audio, update browser or Flash plugin.
LIVE BLOG: First Phase Of Fix 50 Project Underway April 22, 2014 | Bob MoffittThe big "Fix 50" project beganTuesday morning in Sacramento and that means lane closures and likely congestion. Capital Public Radio's Bob Moffitt was out covering the impact on the morning commute.
Fix 50 Answers From CalTrans, City of SacramentoApril 22, 2014 | Pamela WuInsight guest host Pamela Wu speaks with representatives of both Caltrans and the City of Sacramento about the Fix 50 project.